Identify the task point
Measure or estimate the level where the work will actually be carried out, not simply the overall building height.
Locate the machine position
Consider where equipment can physically stand. Ground conditions, entrances and exclusion zones can force the base away from the ideal position.
Identify horizontal distance
If the work point is offset from the base, estimate the horizontal distance and note any structures that must be reached over or around.
Allow the supplier to verify
Provide your measurements as project information rather than treating them as a final machine specification. The supplier should confirm the selected model against manufacturer data.
Separate known measurements from assumptions
List what has actually been measured and what is estimated. For example, the work point may be known from drawings while the final machine standing position is still uncertain. Making that distinction helps a supplier identify where more information is needed instead of treating every figure as fixed.
Recheck the requirement when the site changes
Construction progress, temporary works, stored materials, landscaping and completed finishes can alter where a machine can travel or stand. A height calculation made early in a project should therefore be reviewed if the access route or operating position changes before delivery. The final machine should be verified for the conditions that will exist when the work is carried out.